MALDEB Diary 2002

January 18th, 2002

After a lull over the holidays work has resumed. The concrete folks are in marking the foundation layout, as evidenced by the fact that they have driven a few stakes in the ground and scraped a few meager inches of "top soil" (Ventana Canyon builder talk for "small rocks") down to solid rock.

From here they will drill some one inch holes and epoxy in some re-bar to hold the foundation to the mountain-side. Our builder promises this will take "a few months" and suddenly we'll have a foundation upon which he can construct Casa de la Deuda.

Mar 1st, 2002

The initial foundation work has proceeded very slowly. They have finally "drilled and pegged" about 100 re-bar rods into to the granite -- and we got our first "inspection". So far, we figure these 36-inch pieces of re-bar cost about $1,000 each.


Mar 15th, 2002

Now we're talkin'. The footings have been poured for the first retaining wall and about 4-5 feet of wall has been constructed. We actually see the outline of the lower portion of the house.

April 6th, 2002

Over the past couple of weeks they finished work on the retaining wall - this involved filling the concrete block holes with more re-bar and "special" cement (Translation from Builder-eeze to English: "special" cement costs more than "regular" cement) to keep it from falling over. During the last week they filled in the slope behind the wall with "special" gravel (Translation from Builder-eeze to English: "special" gravel costs more than "regular" gravel) and compacted it - so it is now retaining dirt rather than air. (Translation from Builder-eeze to English: It costs more to retain dirt than air.)

This will become the south side of the lower floor. The large pile of rocks that was
once gone and then reappeared is now starting to be gone again. We don't think there are any bodies buried in there, but who knows?

May - 2002

Our neighbors (Charlie and Susie) donated a set of chairs for us to use while we sit on our lot and imagine what the house will be like when it is done. He and his wife used these same chairs for the same purpose while their house was being built.







We sit and wonder.








A fantastic cactus on our lot. This was a transplant (along with about six others) from where they've been digging, so we are not sure if it will survive the trauma of being moved, but for now it seems ok.




A pretty good overview of the entire project as of May 25.

June 22nd, 2002

Candace and Mike and Sharon Stone on the site (6/22/2002).






June 22nd, 2002

An overview showing the 'front' columns, and some foundation work.






















June 22nd, 2002

A hidden camera (though she seems to know it's there, or just very happy) caught SS stealing rocks from our lot (for her garden landscaping, we think). Can't tell you where she's got them hidden, or this would be a porn site.

July 9th, 2002

A very nice overview of the entire Case Deuda site showing the completed foundation walls to the north side (right) and the completed window support structural steel work on the south side. The back foundation wall shows the approximate level of the 2nd floor. The area in front of the windows will be a patio.

The driveway is shown on the right, awaiting a trench for utilities.

Early to mid-August, 2002

We have a very classy address marker so the contractors can find our lot.

Mid-August, 2002

We have been waiting for weeks for Tucson Electric Power to come out and install a power line from the street to the house so we can get going on the rest of the construction. We have a trench dug (very expensive) and it sits empty while the idiots at TEP figure out what to do to get us power.







August 26th

We have a power transformer that is too small and needs to be upgraded to run all of Mike's computers. Evidently when this was first put in they didn't install a large enough unit and now they can't figure out how to replace it in a timely fashion.

There also seems to be confusion related to the adjustments made to our property line last summer.








Our $8,000 trench awaits the rest of its contents (water, sewer, power, and cable TV lines). The phone line was put in last week and looks awfully lonely there at the bottom of the trench.

The big rock in the middle of the driveway came tumbling down off the side of the hill during a recent monsoon storm. We won't be parking cars in the driveway.

Of course, now that the trench is there, no vehicles can get down the driveway to do any other work on the site. The next big task is to get the lower level slab poured but .....








The power panel holds hot air waiting for TEP to get a connection in place. This is not finish carpentry (we hope) but it is the FIRST WOOD to actually make it to the job site.








By Sept 5th or so, TEP had finally come out and hooked up the new transformer. We now have the required 8 billion kilowatts of power for Mike's computers and his planned inter-galactic satellite communications system.








9/5/2002: The big honkin' black snake laying in the bottom of the trench is the power line.








Thirteen cubic yards of sand waits to fill the trench. It will later turn out that this is only about half as much as we need so another load will be ordered.








The power panel now has a meter (Digital, of course! No turning dials for us!)

The TV cable is also lying at the bottom of the trench in now.








By 9/13/2002, A water line has been run down to the house.

That 'pipe-to-nowhere' is for a special sewer line that carries the 'bad-stuff' up the hill to the actual sewer line. This is a very small line for the amount of you-know-what that Candace and Mike can generate but our builder says that a regular size sewer line (4 inches or so) is too big since the pressure needed to run it up the hill would be too high.



The two visible white pipes are the water and sewer line ... The big trench is to be filled with more sand/gravel.

We thought this was supposed to happen this week, but we are only going by what the builder said early last week. The trench has to be filled before the trucks of other contractors can get down to the job site to do any other work. The trench takes up about 1/3rd of the south side of the driveway width and they would be running with one wheel in the trench the other on the driveway.

The next step is supposed to be the concrete work for the lower floor slab. It seems to me, however, that some work on some plumbing needs to take place before the slab is poured!




September 20 th, 2002:

The trench is now filled.




September 26th, 2002:

Rebar and reinforcing wire is in place. The final inspections are near completion and the 'big-pour' will take place next week.




September 26th, 2002:

Forms for the great room foundation are in place.

The builder forgot to call for an inspection before the slab pour was to happen, but he called the inspector and promised to perform an unnatural act if she would come out quickly to do the inspection. She agreed so the pour is on for Friday the 27th, as planned.




September 27th, 2002...about 9 to 10 am:

The first portion of the slab is being poured. We are happy to see something that resembles the beginnings of a house.




September 27th, 2002...about 11 am:

They are nearly done with the initial (western) half of the slab. This will cure for a while, then they are going to 'score' it to simulate very large floor tiles. The left (eastern) portion of the slab will be poured next week (Monday) we are told.


September 27th, 2002...about 4pm:

The concreate guys are long gone. The first pour is completed and the portion just beyond the chairs is to be done next week.


October 6th, 2002

The remaining downstairs slab and a portion of the garage slab has been completed. The rest of the garage floor slab is to be poured when most of the house is done. The builder feels that there will be too much heavy traffic in this area while things are under construction and this poses a risk of messing up the garage floor.

If you look carefully at the area just in front of the portion of the slab that is completed you can see little gray dots ... these are the footings for the pillars that will be holding up the upstairs deck. This is to be completed early next week.

That spider-webby looking shadow, of course, is from the window frame assembly. The light areas between the shadow lines represent SUN streaming through the windows. Our friends in Seattle don't know about sun, except what they've read in books and seen in movies and on the TV.


October 26th, 2002

A couple of weeks has gone by. We now have some framing and large piles of lumber waiting to become a house.




October 26th, 2002

From above.




October 28th, 2002

Candace is practicing her 'pole-dance' moves for her new part time job at our local strip joint. We are hoping she'll make good tips so we can pay for this project.


November 14th, 2002

The view from the 2'nd floor, approximately where the 'front' door entry will be. The only problem is that we have no idea yet how anyone will get to the front door since there is no current access from anywhere to where the front door will be, except from the INSIDE of the house.


November 27th, 2002

Our new plumbing fixtures have arrived. Now the builder-boys have a place (other than between the foundation and the mountain) to 'vent'.


November 27th, 2002

The upper level sub-floor is starting to go up, sheet by sheet.


December 8th, 2002

Candace, finally standing in the living room area.


December 8th, 2002

Several of the upper level (southwest corner) walls have been erected. Other sections have been pre-built and are to raise into place.


December 8th, 2002

Candace, points in the general direction of the non-existant front entry way. You can see the pre-built walls better in the photo. By the end of the week these will be in place and more walls will be built.


December 8th, 2002

This is the space where the front entry way is supposed to be...but currently you need rock climbing gear to get there. Mike spoke with the construction crew about it again this week and they noted that "the builder has a plan in the back of his head about how this will work out."

I'd like to see it on paper! We may end up having people come in through the garage and lead them to the front entry so they can walk through the front door and take in the beautiful view we had planned for them to see.